Project Updates:

Segment B is currently under construction.

Estimated Complete Date:

Segment B: 4th Quarter 2021 Entire Project: 4th Quarter 2021

Estimated Cost:

TBD

Project Description:

Harris County Precinct One, in partnership with the City of Houston and University of Houston, will reconstruct a 1.5-mile portion of Cullen Boulevard in two phases to transform the existing thoroughfare into a beautiful, bike and pedestrian-friendly street.  A portion of this segment runs through the University of Houston campus.

The two segments include:

  • Segment A: North MacGregor to Wheeler Avenue
  • Segment B: Wheeler Avenue to I-45
Project Benefits:
  • Improves safety and amenities for people walking and biking
  • Enhances street and pedestrian lighting
  • Improves access to transit
  • Enhances landscaping
  • Improves utilities and expands drainage capacity
  • Study100% Complete
  • Design100% Complete
  • Bid100% Complete
  • Construction10% Complete