Summerwood Sidewalks

Sidewalks

NEIGHBOORHOOD:

Summerwood

PROJECT UPDATES:

Phase 1 is complete. A second phase from Woodson Park Drive to Hunters Lake Way is in the design phase and pending permits. It is scheduled to break ground in 2022.

NO. MILES: 1.8

Full size Project Map

Full size map showing completed sidewalks


Summerwood Community Sidewalk project sign

 


PROJECT DESCRIPTION:

Everyone should feel safe walking or biking around their neighborhood. To improve safety in the Summerwood area, Harris County Precinct One has partnered with Municipal Utility Districts 342, 344 and 361 to construct nearly 2 miles of 6-to-8 foot wide sidewalks along both sides of West Lake Houston Parkway from Beltway 8 to Broncroft Court. The project also includes improvements to Woodson Park Drive, Timber Forest Drive and around Beltway 8.

The sidewalks will greatly improve the Summerwood community by adding:

  • Safety for people walking and driving
  • Connections between neighborhoods and parks, retail centers and schools along the corridor
  • Safe access to Wood Creek Middle School and Summer Creek High School by repairing sidewalk gaps along Woodson Park Drive, Timber Forest Drive and under Beltway 8
  • Barrier-free ramps and a pedestrian crossing signal at Woodson Park Drive and Beltway 8
  • A left turn lane onto Broncroft Court from West Lake Houston Parkway to reduce traffic bottlenecks

CONTACT EMAIL:

Capital.Projects@cp1.hctx.net


Study

100% Complete

Design

100% Complete

Bid

100% Complete

Construction

75% Complete