Tidwell Road

Streets

NEIGHBOORHOOD:

Trinity Gardens, East Houston

PROJECT UPDATES:

Construction on Tidwell began in March 2020 after a community meeting was held on February 17, 2020 at the Stephanie Cravens Early Childhood Academy. To view the presentation slides please click here.

EST.  COMPLETION DATE:

Summer 2022

ESTIMATED NO. MILES: 1.1

Full size Project Map

Full size map of project phases


Full size aerial rendering of Tidwell & John Ralston intersection showing additional lanes and turn lanes. Full size aerial rendering of Tidwell & CE King Pkwy intersection showing additional lanes and turn lanes. Full size cross section rendering of Tidwell

Full size aerial view of current Tidwell & John Ralston intersection Full size aerial view of current Tidwell & CE King Pkwy intersection Full size aerial view of current Tidwell RD


PROJECT DESCRIPTION:

Reconstructing Tidwell Road will address growing traffic volumes and enhance safety for every road user. Widening Tidwell from just west of Greens Bayou to CE King Parkway, improving intersections and re-building the Greens Bayou bridge will ease traffic and improve safety. Improvements also include wider sidewalks and improved water drainage.

Construction will last about 28 months. Please use caution in the area while construction crews improve this area.
 

PROJECT BENEFITS:

Long overdue improvements to 1.1 miles of this roadway will:

  • Ease traffic bottlenecks and safety for drivers by widening the roadway, adding turn lanes and improving signals at intersections
  • Improve safety for pedestrians and prevent crashes by adding wider sidewalks
  • Create a safer crossing over Greens Bayou by rebuilding the bridge damaged during Hurricane Harvey
  • Reducing street flooding by improving drainage

CONTACT EMAIL:

Capital.Projects@cp1.hctx.net


Study

100% Complete

Design

100% Complete

Bid

100% Complete

Construction

25% Complete