Van Hut Pedestrian Bridge

Sidewalks

NEIGHBOORHOOD:

Sheldon

PROJECT DESCRIPTION:

Responding to requests from residents in the Sheldon area, Precinct One will construct
a 14-foot pedestrian bridge over a flood control channel connecting two sides of Van Hut Lane.

NO. MILES: .19

See enlarged project map


PROJECT DESCRIPTION:

Everyone should feel safe walking around their neighborhood. To improve the safety of residents walking through the Sheldon area, Harris County Precinct One is adding a pedestrian bridge that will connect two sides of Van Hut Lane.

The addition of the pedestrian bridge will:

  • improve access to healthy recreational opportunities
  • improve safety for pedestrians

PROJECT UPDATES:

The bid phase is concluding and construction is expected to begin August 2021. Construction is estimated to be complete by December 2021.

CONTACT EMAIL:

Capital.Projects@cp1.hctx.net


Study

100% Complete

Design

100% Complete

Bid

100% Complete

Construction

0% Complete